Segment 1: CMC1 Package Aerial Photos And Project Progress Update
16 January 2026
Segment 1: CMC1 Package Aerial Photos And Project Progress Update
(S02 Permatang Damar Laut) Ongoing activities:
Site establishment and machinery mobilization.
(S03 Penang International Airport) Ongoing activities:
Sheet pile installation and site maintenance works.
(S05 FIZ South) Ongoing activities:
Site establishment and machinery mobilization.
(S14 Jalan Tengah) Ongoing activities:
Road widening and temporary drainage works.
(S10 Sg. Nibong) Ongoing activities:
Site establishment in progress and fabrication of reinforcement cage for piling works.
(S18 Bandar Sri Pinang) Ongoing activities :
Hacking of piles in progress.
(S19 Macallum) Ongoing activities:
Site Establishment works - covered parking in progress.