Segment 1: CMC1 Package Aerial Photos And Project Progress Update As Of 21 September 2026
21 Sep 2026
Segment 1: CMC1 Package Aerial Photos And Project Progress Update As Of 21 September 2026
(Depot PSR-A) Ongoing activities:
Site establishment
(S02 Permatang Damar Laut) Ongoing activities:
Site establishment, pile cap and pier column constructions.
(S03 Penang International Airport) Station pier column construction works completed. Ongoing activities:
Site establishment works.
(S04 Sg. Tiram) Ongoing activities:
Bored piling works.
(S05 Fiz South) Ongoing activities:
Site establishment works and mobilization of bore pile machine.
(S06 Fiz North) Ongoing activities:
Bored piling and site establishment works.
(S07 Jalan Tengah) Ongoing activities:
Bored piling and road widening works.
(S08 Spice) Ongoing activities :
Permanent bored pile works.
(S09 Bukit Jambul) Ongoing activities:
Bored piling works and site establishment.
(S10 Sg. Nibong) Ongoing activities:
Utilities relocation works and fabrication of reinforcement cage for piling works.
(S11 Sg. Dua) Ongoing activities:
Bored piling works.
(S12 Batu Uban) Ongoing activities:
Tree cutting works and road diversion works within driving school boundary.
(S13 Jalan Universiti) Ongoing activities:
Permanent precast U-drain installation works.
(S14 Gelugor) Ongoing activities:
Bored piling works and site establishment.
(S15 Penang Waterfront) Ongoing activities:
Permanent bored pile works.
(S16 East Jelutong) Ongoing activities:
TMP implementation and piloting works.
(S17 Sg. Pinang) Ongoing activities:
TMP implementation and piloting works.
(S18 Bandar Sri Pinang) Ongoing activities:
Preparation works for crosshead launching.
(S19 Macallum) Ongoing activities:
Bored piling works.