Prepatory works for Preliminary Test Pile (PTP)

10 June 2025
Prepatory works for Preliminary Test Pile (PTP) at stations and viaducts has began at site

(S02 Permatang Damar Laut) Ongoing activities:
Dilapidation survey, site establishment, soil investigation (SI) works

(V2 Kampung Baruh) Ongoing activities:
Dilapidation survey, site establishment, SI, PTP preparation works

(S10 Sg. Nibong) Ongoing activities:
Dilapidation survey, I&M, site establishment, PTP preparation works

(S14 Gelugor) Maintained Load Test for PTP completed. Ongoing activities:
Dilapidation survey, site establishment.

(V6 Jelutong) Ongoing activities:
Site establishment, SI, PTP piling works

(S18 Bandar Sri Pinang) Maintained Load Test for PTP completed. Ongoing activities :
Dilapidation survey, site establishment, SI.