Project Progress Update (August 2025)
1 August 2025
Project Progress Update (August 2025)
(S02 Permatang Damar Laut) Ongoing activities:
Dilapidation survey, site establishment, soil investigation (SI), PTP preparation works.
(S05 Fiz South) Ongoing activities:
Preparation for PTP works.
(S10 Sg. Nibong) Ongoing activities:
Dilapidation survey, I&M, site establishment work, PTP completed.
(S14 Gelugor) Ongoing activities:
Dilapidation survey, I&M, SI & site establishment works, PTP completed
(S18 Bandar Sri Pinang) Ongoing activities:
Diplapidation survey, site establishment, SI & bored piling works, PTP completed.
(S19 Macallum) Ongoing activities:
Dilapidation survey, site establishment & SI works. PTP completed.
(V2 Kampung Baruh)
Dilapidation survey, instrumentation (I&M), SI & bored piling works. PTP completed.
(V6 East Jelutong) Ongoing activities:
Dilapidation survey, site establishment & SI works. PTP completed.
(02 Kg Baruh)
Site mobilization for bored pile
(06 Bandar Sri Pinang)
Rebar cage for bored piling works
(01 PDL)
Preparation works for PTP
(04 Gelugor)
Construction works for site office (site establishment)