Segment 1: CMC1 Package Aerial Photos And Project Progress Update
31 May 2026
Segment 1: CMC1 Package Aerial Photos And Project Progress Update As Of 31 May 2026
(S02 Permatang Damar Laut) Permanent bored pile works completed. Ongoing activities:
Pilecap works along viaduct.
(S03 Penang International Airport) Ongoing activities:
Pier column & pilecap construction works and site establishment works.
(S04 Sg. Tiram) Ongoing activities:
Traffic Management Plan (TMP) implementation, bored piling works.
(S05 Fiz South) Ongoing activities:
Site establishment works.
(S06 Fiz North) Ongoing activities:
TMP implementation works (road widening).
(S07 Jalan Tengah) Ongoing activities:
TMP implementation works (drainage, road widening).
(S08 Spice) Ongoing activities :
Permanent bored pile works.
(S09 Bukit Jambul) Ongoing activities:
TMP implementation and site establishment works.
(S10 Sg. Nibong) Ongoing activities:
Fabrication of reinforcement cage for piling works.
(S11 Sg. Dua) Ongoing activities:
Demolition of Tapak Pesta and piloting works.
(S12 Batu Uban) Ongoing activities:
No activity (land matters).
(S13 Jalan Universiti) Ongoing activities:
Site establishment works.
(S14 Gelugor) Ongoing activities:
TMP implementation and site establishment works.
(S15 Penang Waterfront) Ongoing activities:
Site establishment works & canal diversion works.
(S16 East Jelutong) Ongoing activities:
No activity (land matters).
(S17 Sg. Pinang) Ongoing activities:
Tree cutting works along viaduct alignment.
(S18 Bandar Sri Pinang) Pier column works completed. Ongoing activities:
Site office establishment.
(S19 Macallum) Ongoing activities:
Site establishment & site office works.