LONG TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ON JALAN TENGAH (SUNWAY TUNAS TO PERSIARAN MAHSURI)

28 Nov 2025
31 Jan 2026

Activity

Preliminary Utilities Works

Description

Please be informed that long-term intermittent partial night lane closure will be implemented on Jalan Tengah from 28 November 2025 to 31 January 2026. The activity will take place from 10:00 pm to 5:00 am.

Share :

LONG TERM INTERMITTENT PARTIAL LANE CLOSURES ALONG JALAN TUN DR AWANG (SETIA SPICE – I AVENUE)

25 Nov 2025
17 Jan 2026

Activity

TREE CUTTING

 

Description

Please be informed that long-term intermittent partial night lane closures along a stretch of Jalan Tun Dr Awang will be implemented from 25 November 2025 to 17 January 2026. The closure will be implemented from 10:00 pm to 5:00 am.

Share :

Long-Term Intermittent Partial Lane Closures On Tun Dr Lim Chong Eu Expressway

19 Nov 2025
31 Dec 2025

Activity

Tree Cutting And Road Widening Works

Description

Please be informed that long-term intermittent partial lane closures on the Tun Dr Lim Chong Eu Expressway will be implemented from 19 November 2025 to 31 December 2025. The closures will take place between 9:00 am and 5:00 pm.

Share :

Long-Term Partial Lane Closure On Jalan Sultan Azlan Shah (Jalan Sultan Azlan Shah (Persimpangan Hilir Pemancar – Giat Mara Bukit Gelugor))

15 Nov 2025
30 Apr 2026

Activity

Site Preparation, Tree Cutting, Road Widening and Drainage Work

Description

Please be informed that a long-term partial lane closure along Jalan Sultan Azlan Shah (both directions) will be implemented 24 hours a day from 15 November 2025 to 30 April 2026.

Share :

Long-Term Partial Lane Closures Along Jalan Sultan Azlan Shah (Both Directions) (Sungai Tiram)

22 Sep 2025
31 Dec 2025

Activity

To facilitate preliminary works for the LRT Penang: Mutiara Line (PML) project, including tree cutting, soil investigation and utility relocation.

Description

The long-term partial lane closures on both directions along Jalan Sultan Azlan Shah, near the Sungai Tiram area, will be implemented from 22 September 2025 to 31 December 2025. The closures will be carried out for 24 hours a day over a period of three (3) months and ten (10) days. During the implementation of the lane closures, the fast lanes in both directions, along the stretch between Penang International Airport and the Jalan Mayang Pasir Traffic Light Junction will be affected.

Share :

Short-Term Partial Lane Closure On Inner Road Near Giant Bayan Baru (Jalan Tengah)

13 Oct 2025
23 Oct 2025

Activity

To facilitate relocation of TNB 132kV cable for Penang LRT: Mutiara Line (PML) Project

Description

Short-term partial lane closures at inner road in front Giant Bayan Baru will be implemented from 13 October 2025 to 23 October 2025. The closures will be carried out between 10:00 pm to 5:00 am

Share :

Partial Night Lane Closure On Jalan Tengah Between The Intersections Of Persiaran Mahsuri And Jalan Tun Dr. Awang

16 Oct 2025
09 Nov 2025

Activity

Piloting works

Description

A partial night lane closure will be implemented on Jalan Tengah, near Sunway Tunas residential area and Bayan Baru Police Station, from 16 October 2025 to 9 November 2025.