LONG TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURES ALONG JALAN SULTAN AZLAN SHAH (SUNNY POINT JUNCTION – USM FIELD)

03 Dec 2025
31 Jan 2026

Activity

Tree cutting works

Description

Please be informed that long term intermittent partial night lane closures along a stretch of Jalan Sultan Azlan Shah will be implemented from 3 December 2025 to 31 January 2026. The closure will be implemented from 10:00 pm to 5:00 am.

Share :

SHORT TERM PARTIAL NIGHT LANE CLOSURES ON JALAN SULTAN AZLAN SHAH (GELUGOR)

02 Dec 2025
05 Dec 2025

Activity

Tree cutting works

 

Description

Please be informed that a short-term partial night lane closures on Jalan Sultan Azlan Shah (near Gelugor) will be implemented from 2 December 2025 to 5 December 2025. The closure will take place from 10:00 PM to 5:00 AM.

Share :

LONG-TERM INTERMITTENT PARTIAL LANE CLOSURE ALONG A STRETCH OF JALAN TENGAH

28 Nov 2025
31 Jan 2026

Activity

Road widening and drainage relocation

 

Description

Please be informed that long-term intermittent partial lane closures will be implemented along a stretch of Jalan Tengah, between Jalan Tengah Apartment and Balai Bomba Bayan Baru from 28 November 2025 to 31 December 2025.

Share :

LONG TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ON JALAN SULTAN AZLAN SHAH BETWEEN THE JALAN TENGAH APARTMENT AND SNAKE TEMPLE. (JALAN SULTAN AZLAN SHAH)

28 Nov 2025
31 Jan 2026

Activity

Preliminary utilities works

 

Description

Please be informed that long term intermittent partial night lane closures will be implemented on Jalan Sultan Azlan Shah, between the Jalan Tengah Apartment and Penang Snake Temple from 28 November 2025 to 31 January 2026.

Share :

LONG -TERM PARTIAL INTERMITTENT NIGHT LANE CLOSURE ALONG JALAN SULTAN AZLAN SHAH

28 Nov 2025
31 Jan 2026

Activity

PRELIMINARY UTILITIES WORK

 

Description

Please be informed that long term partial night lane closures along a stretch of Jalan Sultan Azlan Shah, will be implemented from 28 November 2025 to 31 January 2026.

Share :

LONG TERM INTERMITTENT PARTIAL NIGHT LANE CLOSURE ON JALAN TENGAH

28 Nov 2025
31 Jan 2026

Activity

Preliminary utilities work

 

Description

Please be informed that a long-term partial night lane closures on Jalan Tengah will be implemented from 28 November 2025 to 31 January 2026. The closures will take place from 10:00 pm to 5:00 am.

Share :

LONG TERM PARTIAL NIGHT LANE CLOSURE ON JALAN TENGAH

28 Nov 2025
31 Jan 2026

Activity

Preliminary Utilities Works

Description

Please be informed that a partial night lane closure will be implemented on Jalan Tengah, from 28 November 2025 to 31 January 2026.